    How Long Does It Take to Build a Pool in Houston?

    The short answer: most custom gunite pools in Houston take 8–14 weeks from permit approval to completion. Here's a detailed breakdown of each phase and what affects the timeline.

    Design Phase: 2–4 Weeks

    The design phase includes your initial consultation, 3D rendering, revisions, material selection, and engineering. Rushing this phase is a mistake—investing time here saves money and headaches during construction.

    Permits: 2–4 Weeks

    Permit processing varies by jurisdiction. City of Houston typically takes 2–3 weeks, while surrounding cities and counties may take 1–4 weeks. HOA reviews add 1–3 weeks. We submit permits immediately after design approval.

    Excavation: 2–5 Days

    Excavation is weather-dependent and varies by pool size and soil conditions. Most pools are excavated in 2–3 days. Rain can pause excavation due to safety concerns and soil stability.

    Steel, Plumbing & Electrical: 1–2 Weeks

    Rebar installation, plumbing rough-in, and electrical conduit placement typically take 5–10 working days. Each phase requires inspection before proceeding.

    Gunite: 1–2 Days + Curing

    The gunite shell is shot in a single day for most pools. A 7–14 day curing period follows, during which the shell is kept moist. Tile and coping work can begin after initial curing.

    Finishing: 3–5 Weeks

    Tile, coping, decking, equipment, plaster, and fill complete the project. This is the longest phase due to the sequential nature of the work and drying/curing times between steps.